New school doors keep kids safe
7th July 2021
Replacement fire doors at two schools are being installed by Procast as part of an internal upgrade programme.
The project involved a total of 90 door sets at Cross Arthurlie Primary and Hillview Primary Schools in East Renfrewshire.
The six-week programme, which is due to be completed by the start of August, saw 60 stairwell fire doors and 30 corridor fire doors installed at both locations, as well as:
- New fanlights and screens
- At Cross Arthurlie Primary School – one new corridor timber double doorset and partition
- Making good of all wall, floor and ceiling finishes
- Complete a site survey to check dimensions on site before ordering material and components or commencing works
- Works associated with the fire alarm system (for automatic closers, magnetic hold-open devices), intruder alarm and firefighting equipment and signage
< back