South Lanarkshire Council

Project:
South Lanarkshire Council – Package 93
Client:
South Lanarkshire Council
Location:
South Lanarkshire
Value:
£400,000

Working as the Principal Contractor we were appointed to carry out a full overhaul of existing council properties, predominantly render and roofing.

  • Hammer test full building, hack off and dub out as required, apply a full Alumasc over coating system, including scrimming and pinning where required all in line with manufacturers specifications and recommendations.
  • Remove, supply and fit concrete lintels where defective
  • Paint existing concrete cills
  • Remove, supply and install new uPVC downpipes with associated fitments
  • Renew all existing SVP’s and make good connections into live properties
  • Full mastic sealant to all properties
  • Supply & erect scaffold
  • Strip existing tile roof and felt, and re-do roof sarking with 12mm WBP external boarding
  • Removal of chimneys
  • Re-tiling roofs in Marley Plain tiles with associated battens and underlay and all associated fitments.
  • Removal of existing fascia and soffit and replaced with new white uPVC
  • Take down existing cast iron gutters and replace with new black UPVC (or aluminium if over 3 storeys), profile to match existing.
  • Renew and removal of all electrical fittings and satellites and aerials.
  • Full inspection of gas flues and issuing of CP12’s from our in-house gas teams.

To successfully complete all works to a high standard while maintaining public safety, we complete rigorous risk assessments and implement clear risk management processes. During site set up, our Operatives clearly define site boundaries between the works and the public. To ensure the safety of staff, residents and the public, we erect and maintain boarding throughout the contract. In line with current legislation, the boarding displays ‘no entry’ and ‘Operatives at work’ signs. To minimise the impact of contracted works, we continually meet with residents prior to commencement and schedule works at times that cause the least disruption.

Working efficiently to a high standard, we were able to complete our most recent works programme 2 weeks ahead of schedule, saving the client £3500 and avoiding any over-run costs. We did this by effectively planning works prior to commencement and efficiently managing each phase of the contract and our approved subcontractors and suppliers. By implementing our enhanced safety measures, we successfully mitigated safety risks, resulting in zero reportable accidents.

< back

Energy Brochures

Click To Download